As the Peninsula Road Safety & Revitalization Project is nearing completion, we wish to provide the following updates of work to be completed:
Week of July 15th
- Paving will be completed between Bay and Forbes.
Week of July 22nd
- Road line painting and sign installation will be completed.
- Laying of soil will begin for landscaping purposes.
Week of July 29th
- Site cleanup will occur over 1-3 weeks. We are waiting on a few final touches, including the arrival and installation of flashing lights for the crosswalks.
September
- Trees, shrubs, and grass will be planted, weather permitting.
Important Considerations:
- The week of July 22nd, the intersection at Bay Street and Peninsula Road will become a 4-way stop. Please use caution and follow all traffic signage while adjusting to this change.
- Landscaping: While the utilities and hardscaping will be completed in July, landscaping will follow later. We want to avoid planting new trees, shrubs, and grass during the hot August season to prevent stress on the plants. All plantings will be delayed until September or shortly after when the summer heat has cooled off to give them the best start.
For the latest information and project updates, please visit our current construction project website at: Ucluelet.ca/Peninsula-rd
If you have any questions, or require further information regarding this project, please contact:
We thank you in advance for your cooperation and understanding during this construction period.