Community Notices

Construction Notice - Peninsula Road Improvements (Phase 1) Begins January 23, 2024


Hazelwood Construction Services Inc., working on behalf of the District of Ucluelet, will be starting construction of Peninsula Road Improvements (Phase 1) in January 2024. Phase 1 includes upgrades from Seaplane Base Road to Bay Street. The focus of this first phase of work is to provide continuous and improved cycling and pedestrian routes on the southwest side of the road (opposite the harbour) and storm system replacement between the Sea Plane Base Road and Lyche Road Outfall.

The construction works are expected to be completed in four stages. The general schedule and stages are outlined below:

  • Mobilization: January 23, 2024
  • Stage 1: Sea Plane Base Road to Lyche Road (February 2024 to March 2024)
  • Stage 2: Lyche Road to Lyche Road Outfall (March 2024)
  • Stage 3: Lyche Road to Bay Street (March 2024 to April 2024)
  • Stage 4: Surface Improvements (April 2024 to May 2024)
  • Substantial Completion: May 31, 2024

More information on the Peninsula Road Safety & Revitalization Project can be found here:

Peninsula Road Safety & Revitalization Project

View the construction notice here (Click to enlarge):

240117 Construction Notice Peninsula Road Improvements Phase 1 Page 1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

240117 Construction Notice Peninsula Road Improvements Phase 1 Page 2